CAF Risk in Multilayer PCBs: Material, Geometry and Qualification Conditions

Review PCB CAF risk through material construction, conductor geometry, process changes and a traceable qualification plan.

Discuss your project ↗

A useful CAF review asks whether the proposed board construction, conductor geometry and manufacturing process have been evaluated under relevant moisture and electrical-bias conditions. Specifying a laminate as “CAF resistant” is a starting point, not evidence that every layout made from it has the same reliability.

This guide helps engineers and purchasers prepare that review. It does not assign a universal spacing rule, accelerated-test duration or field-life prediction. Those decisions need the product’s operating conditions and an agreed qualification plan.

First identify the insulation failure being investigated

Conductive anodic filament growth is an internal electrochemical migration failure mechanism. A low insulation-resistance reading alone does not identify it: surface leakage, contamination, damaged insulation and other conductive paths may produce similar electrical symptoms. The published scope of IPC-9691B distinguishes internal migration from surface effects and identifies material and processing variables involved in the evaluation.

For a failed assembly, start with a net-to-net fault map and the conditions under which the fault appears. Record humidity exposure, applied voltage, polarity, duration and whether the reading changes after drying. Preserve the sample for analysis instead of repeatedly stressing or cleaning it without a documented plan. A changed reading after drying is evidence to investigate, not proof of a particular mechanism.

Specify the construction, not only the laminate family

The board includes reinforcement, resin, copper and the effects of fabrication. Capture the approved core and prepreg grades, glass styles, dielectric thicknesses and material substitutions. The PCB material construction guide explains why a broad label such as FR-4 is insufficient for a repeatable purchase specification.

As a concrete material example, Isola describes its 370HR laminate and prepreg as using E-glass reinforcement and offering CAF resistance. Its 370HR product information presents this alongside separate thermal and electrical properties. Do not substitute glass-transition temperature, dielectric strength or a material recognition number for application-specific CAF evidence. Request the relevant report and its construction, coupon and test conditions.

A practical procurement record has three columns: the property required by the design, the evidence offered by the supplier, and any gap between the tested construction and the ordered board. An unexplained gap deserves an engineering disposition before an alternate material enters production. “Equivalent FR-4” should not silently replace a named, evaluated construction.

Review the geometry that the test actually represents

Identify closely spaced conductors with sustained potential differences. For each critical pair, record the conductor features, drill geometry, layer relationship and orientation within the reinforcement. A finished-hole diameter and center-to-center pitch do not by themselves describe the dielectric separation relevant to every failure path.

IPC-TM-650 Method 2.6.25, revision C defines CAF test structures and distinguishes drilled-hole dimensions from finished-hole dimensions when establishing the test geometry. Its scope covers evaluation of materials, designs and manufacturing changes. Use the selected method’s full requirements rather than extracting one coupon spacing as a product design rule.

Bring the critical locations into the stackup review. Ask whether the intended coupon represents the relevant construction and conductor arrangement. A coupon designed to compare hole-to-hole behavior may not answer a question about a different internal conductor pair. Document what the selected test covers and what remains outside its scope.

Example: compare two proposals without hiding the variables

Consider an illustrative industrial controller with two fabrication proposals. Proposal A retains the qualified laminate but changes drilling and press-fit assembly conditions. Proposal B retains the established fabrication route but changes the laminate and prepreg combination. Neither proposal can be accepted solely because a supplier attaches a generic “CAF pass” report.

For A, request an explanation of how the process change is represented in the evidence. For B, compare the tested material construction with the proposed stackup. If both material and process change at once, a result may show that the new combination behaves differently without identifying which change caused it. Agree whether the immediate purpose is screening a complete construction or investigating a specific variable.

Keep the baseline board files and build record attached to the comparison. List unchanged items as well as deliberate changes. This makes a later failure-analysis discussion more useful than comparing two reports whose samples cannot be traced back to a controlled configuration.

Write a qualification request that can be reproduced

  • Purpose: material selection, process change, supplier comparison or failure investigation.
  • Samples: board and coupon revisions, construction, manufacturing lots and the reason for the sample quantity.
  • History: relevant storage, fabrication, assembly and conditioning steps.
  • Conditions: named method and revision, environment, bias, polarity, duration and measurement procedure.
  • Acceptance: the agreed failure criterion, treatment of invalid channels and required data retention.
  • Investigation: sample handling after a failure and the analytical evidence needed to identify its cause.

Have the test laboratory review departures from the selected method before the run. Revision C explicitly cautions that the method was not designed for bias above 100 VDC; higher-voltage work needs an appropriately engineered setup and safety review. This note is not a procedure for operating that equipment.

Separate a screening comparison from a release decision

A screening experiment can help select which construction deserves further investigation. A release decision must answer whether the evidence supports the intended product and its controlled manufacturing route. Those purposes can use related tests, but they should not be confused. A promising comparison under one set of conditions is not automatically a complete qualification for another board.

Start the review by writing the decision in a sentence. For example, the team may need to determine whether an alternate prepreg construction can replace the current one without changing the agreed insulation-reliability requirements. That question identifies the proposed change and the baseline. A vague request to test for CAF leaves the laboratory to guess which differences matter.

List the variables the comparison will hold constant and the ones it deliberately changes. Preserve the material identities, construction details and fabrication records for both sample groups. If sample preparation differs, explain why and identify the effect on interpretation. A result with several uncontrolled differences may still justify further work, but it should not be presented as isolating the effect of one material property.

Before ordering the test, agree what each possible outcome would mean. A failure might reject the proposed substitution, trigger additional analysis or require another experiment with better control of a confounding variable. A pass may support the specified change only within the tested scope. Making these decision rules explicit prevents a report from being interpreted differently by purchasing, engineering and the laboratory after the results arrive.

Build a traceable map from the product to the test vehicle

Create a short matrix connecting each critical product feature to the test feature intended to represent it. Include the conductor relationship, dielectric construction and relevant process history. Record any difference instead of implying that every coupon reproduces the whole product. The matrix makes it easier to see whether a test answers the most important product question or simply uses a convenient existing coupon.

For example, a product review may identify a particular biased conductor pair near a mechanically stressed connection. A generic material report may use a different geometry and omit the relevant assembly history. The report can still be useful background, but the gap requires an engineering decision. Ask the laboratory and fabricator how the proposed evidence addresses that gap rather than assigning a universal safety factor without a supporting model.

Use the same map when reviewing a later design change. Moving a via, changing a dielectric construction or altering a manufacturing step may affect the relationship between the product and the evidence. Not every change requires the same response; the controlled review should identify which assumptions changed and whether the existing qualification remains applicable. Record the reasoning even when the conclusion is that no additional test is necessary.

Plan data review and failure analysis before the test

Request enough measurement history to distinguish a stable result from a transient event or an invalid channel. Agree how interruptions, equipment anomalies and missing data will be identified in the report. A pass summary without the underlying conditions and exception record can conceal uncertainty that matters to the release decision. Do not silently treat an unmeasured interval as proof that resistance stayed above the acceptance criterion.

If a channel fails, retain its identity and the corresponding physical sample location. Discuss the next analytical steps with the laboratory before destructive preparation. A poorly planned sectioning operation can miss a localized path or destroy evidence needed to distinguish internal migration from another mechanism. The objective is to identify the cause supported by observations, not to label every low-resistance event as CAF.

Keep failed samples, unaffected comparison samples and relevant manufacturing records linked through unique identifiers. Photograph and document handling steps as the investigation proceeds. If drying, cleaning or additional electrical stress is applied, retain the sequence and the reason, because the sample may no longer represent its original condition. These controls support interpretation without prescribing a hazardous test procedure.

Close the investigation with a specific disposition. State which observed mechanism is supported, which alternatives remain unresolved, and what change is required before another build. Then connect that disposition to the purchase specification, approved construction and change-control process. A corrective action is incomplete if the next order can still substitute the same unreviewed material or process that created the evidence gap.

Use the result for the decision it supports

A pass applies to the evaluated sample population and conditions. It is not, by itself, a guarantee of a particular number of years in service. Similarly, a failure should trigger investigation of the actual path before the entire laminate family is rejected. Ask for resistance-versus-time data, anomalous channels and failure-analysis observations, not just a cover-page statement.

At release, connect the approved result to material substitution control and the fabrication revision. Reassess the evidence when a change affects a variable on which the qualification depends. The review should give purchasing a clear acceptance decision and engineering a traceable basis for that decision.

Preparing a reliability-sensitive build? Review the PCB fabrication requirements, then send the stackup, critical conductor geometry and qualification requirements for a project-specific discussion.