An assembly variant is useful only when the manufacturing package identifies the same build in every file. A correct variant definition does not rescue an assembly drawing exported for the base design or a bill of materials copied from yesterday’s folder. Before sending an Altium project for assembly, review the generated package as the recipient will use it: without access to the engineer who remembers which options were selected.
This guide concentrates on the release checks for an existing variant, not on a complete introduction to Altium Designer. It uses a hypothetical controller with Standard and Extended versions to show how a reviewer can detect inconsistent outputs. The workflow is a proposed review method. Confirm interface names and behavior in the documentation for the installed software version before applying it to a production project.
Separate the board revision from the assembly identity
Altium’s design variants documentation distinguishes assembly variants from fabrication variants. Assembly variants can share a bare board while changing component population, parameters, or alternate parts. A fabrication variation can affect the manufactured board, including overlay information. Therefore, a shared project name does not by itself prove that two output packages use an identical bare board.
Start the review with a release identity containing the project revision, bare-board revision, assembly variant name, assembly revision, and intended quantity. Decide which identifier belongs on the purchase order and which belongs on the completed assembly label. A fabricator buying blank boards needs a board definition; the assembler also needs the population definition. Keeping those decisions explicit prevents an assembly option from silently becoming a board revision.
In the hypothetical example, both versions use bare board C. Standard omits an optional connector and its support components, while Extended includes them. Both packages must identify board C, but they need distinct assembly identities. If the Extended version later requires a different printed legend, the team must evaluate that fabrication change rather than continuing to call the difference population-only.
Use a short difference register as the review starting point
Create a register of the components that are expected to change between versions. Record the physical reference designator, fitted state, intended manufacturer part number, and the reason for each difference. Include changed resistor values and alternate components, not just the conspicuous missing connector. The register is a review aid derived from the approved design; it should not become an independent, manually maintained replacement for the CAD definition.
For the example, suppose J4 is omitted in Standard and fitted in Extended, R18 has a different approved value, and U7 uses an approved alternate. These are three different checks. J4 needs a population check. R18 needs a parameter and purchasing-identity check. U7 needs an alternate-part check with the appropriate package and pin mapping review. Treating all three as a single checkbox called variant checked hides the important distinctions.
Have a reviewer who did not create the outputs compare that register with the exported documents. The reviewer should be able to identify each intended difference without opening a chat conversation or inferring the meaning of a folder called latest. Any unexplained change in the exports becomes a question to resolve before the kit is sent.
Confirm what the variant definition actually stores
The official Variant Management dialog documentation describes fitted, not-fitted, and alternate-part states, as well as local parameter changes. It also explains where variant information and alternate parts are stored. Preserve the relevant project files with the release; a standalone board file should not be assumed to contain every decision needed to reproduce the assembly outputs.
A visible value change is not sufficient purchasing evidence. Check that the fields consumed by the BOM template carry the intended information. For R18, a changed displayed resistance paired with the previous manufacturer’s part number creates an internally inconsistent instruction. Decide which approved field controls purchasing and verify that the exported value, tolerance, package, and part number describe the same component.
For U7, review the alternate against the circuit requirements separately from its appearance in the software. A library selection is not an engineering approval. Check the chosen component revision, required electrical behavior, pin functions, and package suitability. Keep the approval reference with the release review so a later library update cannot be mistaken for an already reviewed substitution.
Inspect the Output Job variant scope
Altium’s Output Jobs documentation describes two scopes: one variant for applicable outputs throughout the job, or a separate variant selection for each applicable output. The base design can also be selected. Review the actual scope and selections in the saved job instead of assuming that the variant visible elsewhere in the project controls every export.
A job with individual selections deserves a line-by-line check. The BOM could name Extended while an assembly drawing still uses the base design. Write the expected source and variant beside each deliverable in a release checklist. Include fabrication outputs in the review, while recognizing that their relationship to assembly variants differs from the population-sensitive outputs. The official documentation describes cases where a fabrication output falls back to the base design.
Save the reviewed job with the project revision. Generate into a clean, release-specific destination so old files cannot survive unnoticed beside new ones. If filenames include identifiers supplied through parameters, inspect the actual generated names and title blocks. A correctly named folder can still contain a document whose internal identification describes a different build.
Reconcile the BOM by designator before checking totals
Open the exported BOM and find every reference in the difference register. Check whether omitted parts are excluded or retained with an unmistakable not-fitted indication according to the agreed format. Do not rely on blank quantity cells or color alone to communicate the instruction. The recipient should know whether a row is a purchasing requirement, an informational reference, or an intentional omission.
For fitted components, expand grouped designator lists during review when necessary. A group containing R18 and several unchanged resistors can conceal an incorrect grouping rule. Compare the designator set, quantity per assembly, and purchasing identity together. Matching the total number of pieces does not prove that the correct references receive the correct parts.
Use a simple quantity example to expose unit confusion. If an order contains thirty Extended assemblies and each requires two pieces of a selected connector, the design demand is sixty pieces. Ten Standard assemblies with that connector omitted add zero demand for it. Procurement allowances are a separate agreed quantity; they should not change the per-assembly BOM definition or disguise a mistaken population count.
Cross-check drawings and placement information
Inspect the rendered assembly drawing at a readable scale, including both sides when applicable. Locate J4 and verify that its presentation communicates the Standard omission correctly. Then locate R18 and U7 and confirm that any displayed values or notes agree with the BOM. A reviewer should not need to choose between conflicting documents during line setup.
Review the placement file’s reference designators and population scope against the intended assembly. Agree how intentionally absent parts are handled by the receiving process. For included parts, check side, origin convention, coordinate units, and rotation interpretation through the normal assembly release review. Variant correctness does not independently prove those geometric details, so preserve the distinction between population validation and placement validation.
For the broader file-release sequence, use the Altium manufacturing output guide. The variant review adds a consistency check across that package. It does not replace independent inspection of drill data, board geometry, assembly orientation, or the supplier’s accepted file formats.
Challenge the package with a deliberate mismatch
A useful review exercise is to ask what would reveal a Standard drawing accidentally placed in the Extended folder. The answer should be an explicit variant identifier plus the expected population differences, not the engineer’s memory of the export time. Check whether the receiver can detect the mismatch using only the released documents and the purchase order.
Consider another hypothetical error: R18 changes correctly in the BOM, but the assembly drawing still displays the old value. Resolve the source or template issue and regenerate the affected package. Editing the exported PDF by hand might make one file look right while leaving the reproducible output process wrong. Preserve a record of the cause and the regenerated files that were reviewed.
After regeneration, compare the complete package with the previous candidate. A narrow fix can unintentionally change other outputs if a job selection or parameter also changed. Review the expected difference register again and investigate unexpected differences. Store the rejected candidate separately from the approved release so neither the purchasing team nor the assembler can accidentally use it.
Release a package that can be reproduced
- Identify the board revision and assembly variant separately.
- Record fitted-state, parameter, and alternate-part differences.
- Check the saved Output Job scope and each applicable selection.
- Reconcile BOM designators, quantities, and purchasing identities.
- Compare assembly drawings and placement scope with the same build.
- Inspect generated filenames, title blocks, units, and revision labels.
- Archive the reviewed project, job configuration, outputs, and approvals.
- Define which files must be regenerated after a design or library change.
The final handover should include a concise manifest listing the approved files, variant, quantities, and review status. Record the Altium version used to generate the package, especially when another engineer will reproduce it later. A repeatable review is easier when the next person can distinguish the source design, output configuration, and delivered artifacts without reconstructing the author’s working session.
Keep this check within the broader PCB design and release workflow. For a prototype PCB build, identify whether the request includes bare boards, assembled variants, or both. To review an assembly-variant package, send the revisioned BOMs, drawings, quantities, and any unresolved differences. Contact Stan@4PCBA.COM or WhatsApp +86 185 7700 2040.